Tuesday, November 10, 2009

Resolved - UO-1492 myPurdue Portal Unscheduled Outage

11/10/2009 6:30 AM - 11/10/2009 6:43 AM

The ITaP services below were unavailable.
The issue is resolved as of 11/10/09 6:43 AM.


Resolved - UO-1493 Authentication & Authorization Services Unscheduled Outage

11/10/2009 10:25 AM - 11/10/2009 10:59 AM

The ITaP services below were unavailable.
The issue is resolved as of 11/10/09 10:59 AM.

Users were unable to authenticate when logging into ITaP web pages.


Resolved - UO-1494 ITaP Web Services - ColdFusion/ASP Unscheduled Outage

11/10/2009 12:04 PM - 11/10/2009 1:10 PM

The ITaP services below were unavailable.
The issue is resolved as of 11/10/09 1:10 PM.

E-mails from outages were not being sent so admins restarted ColdFusion Node A on the prod servers and it appears that email is working properly now.


Completed - RFC-5878 myPurdue Portal Downtime 11-10-09

11/10/2009 6:30 AM - 11/10/2009 7:00 AM

The myPurdue Portal will be unavailable from 6:30 AM to 7:00 AM on November 10, 2009.


Approved - RFC-5857 Remove Distributed File Replication from ColdFusion Production Cluster

11/10/2009 12:00 PM - 11/10/2009 1:00 PM

On Tuesday, 11/10/2009, between noon and 1:00 PM, Web Services will be disabling the replication between the production ColdFusion nodes (wpvwebcfa01a and wppwebcfa01b) and instead have modified the Deploy tool that developers use to migrate their code so that it will copy the files to *both* nodes. This should alleviate the problems that developers have seen (files disappearing, old files showing up, replication delays, etc.) Customers should see no difference.


Completed - RFC-5880 Replacement of a production SQL Server's SSL certificate

11/10/2009 3:45 PM - 11/10/2009 4:00 PM

On Tuesday, November 10th at 3:45 PM, the SSL certificate upon the wpvsqlhfs01 SQL Server will be replaced. Installation will require a reboot of the SQL Server.